Ithaca Builds

Mapping, photos and information for Ithaca construction and development projects

Thurston Avenue Apartments Final Building Photos

September 6, 2014 // by Jason Henderson

The three building, three story, 57 bedroom, 18 unit Thurston Avenue Apartments project in Cornell Heights has been completed for occupancy just in time for the start of the semester. Below are some final photos, and a brief project narrative:

The project site plan was approved by the City of Ithaca Planning Board last June, 2013. The structure foundations were dug back in December, with some foundation work over the winter, and then insulated concrete form (ICF) block foundation walls in February. The unusually prolonged and severe winter prevented a lot of early site work (i.e. underground plumbing), but by March, light wood framing for the three-story structures began (framing by Compass Builders), and showed good progress throughout April and May. Roofing started-up and finished in May, and by June, the Marvin windows had been fully installed. Brick veneer base and stone caps began installation in June, and finished by July. Throughout July and August, the façade Hardie stucco panels, side and window trim, roof fascia, and other exterior building finishes were installed, along with landscaping: the project contains a parking lot with 19 parking spaces, concrete curbing and sidewalks, several stone retaining walls along the sloped hillside facing the Thurston Ave/Highland Ave intersection, and ample trees and shrubs. Some landscaping work still remains around the hillside, but certificates of occupancy have been completed, and folks have moved-in.

The project is owned and developed by RABCO Highland House, the operator/owner of the adjacent apartment building, Highland House. Construction was completed by G.M. Crisalli & Associates out of Syracuse, NY, with design by HOLT Architects, and landscape architecture by Trowbridge Wolf Michaels Landscape Architects.

Thurston-Ave-Apartments_09011411

Thurston Ave Apartments Inventory

Thurston-Ave-Apartments_09011409

Thurston-Ave-Apartments_09011407

Thurston-Ave-Apartments_09011404

Thurston-Ave-Apartments_09011410

Thurston-Ave-Apartments_09011405

Thurston-Ave-Apartments_09011416

Thurston-Ave-Apartments-Birdeye

Three-Bedroom-Thurston-Ave

Cayuga Place Residences Photo Update

September 1, 2014 // by Jason Henderson

The Cayuga Place Residences project has moved forward since the last check-in on August 20th for steel assembly: the second floor hollow core plank has been set in place between all 16 columns, and it looks as if the ends have been filled solid, which produces a higher-strength floor. Steel beams span the length of the third floor, so we should see the next floor set this week or next.

Supporting foundation work began early May, and finished-up later on in June, then block work began late June/early July.

The building will be a 7-story, 45-unit, 49,244 GSF project, being developed by Bloomfield/Schon + Partners, with construction by Turnbull-Wahlert Construction, both firms out of Cincinnati, Ohio.

Cayuga-Place-Residences_09011414

Cayuga-Place-Residences_09011413

Cayuga-Place-Residences_09011412

Cayuga-Place-Residences_09011406

Cayuga-Place-Residences_09011401

Collegetown Dryden Project Site Plan & Renders

August 26, 2014 // by Jason Henderson

Novarr-Mackesey submitted plans for a three-building series of six-story structures along Dryden Road from College Avenue to Linden Avenue last month: renders and site plan images are below. The sites were assembled over the course of several years as outlined by Ithacating’s Post here, under the name Dry-Lin, LLC. The designs are done by ikon.5 architects, the same as for the Collegetown Terrace Project.

The total project would create 141 studio units, 11 parking spaces, 10,510 square feet of retail, and 9,000 square feet of cellar space for a grand total of 107,302 square feet for all three buildings (breakdown below).

Collegetown Dryden Project - Sketch Plan Presentation - 07-22-14_Page_1

Collegetown Dryden project

Novarr-Dryden-College-Ave-Ithaca-062414-21

Novarr-Dryden-College-Ave-Ithaca-0624142

Collegetown Dryden Project - Sketch Plan Presentation - 07-22-14_Page_3

Collegetown Dryden Project - Sketch Plan Presentation - 07-22-14_Page_4

Collegetown Dryden Project - Sketch Plan Presentation - 07-22-14_Page_5

Collegetown Dryden Project - Sketch Plan Presentation - 07-22-14_Page_6

Thurston Avenue Apartments August 20th Photos

August 23, 2014 // by Jason Henderson

RABCO Highland House‘s 18-unit Thurston Avenue Apartments project looks to be wrapping-up just in time for the start of classes. There’s still a bit of facade work to be completed, but the units look complete from the outside. In the space of six days since last post (August 14th to the 20th, when these photos were taken), the driveway and parking lot has been asphalted and striped, all facade and roof fascia panels have been hung on the corner buildings, and the center building’s street-facing facade has been completed, but the sides are missing a few small sections of stucco panelling, which may be done by the time of writing. The site should be seeded and strawed or turfed any day now. The project got a late start (like many) due to the prolonged and intense winter- photos from March.

The construction was done by GM Crisalli & Associates, and designed by HOLT Architects, with landscape architecture by TWMLA.

Thurston-Ave-Apartments_08201406

Thurston-Ave-Apartments_08201407

Thurston-Ave-Apartments_08201410

Thurston-Ave-Apartments_08201414

Thurston-Ave-Apartments_08201415

Three-Bedroom-Thurston-Ave

Thurston-Ave-Apartments-Birdeye

Cayuga Place Residences Steel Assembly

August 20, 2014 // by Jason Henderson

Structural steel assembly began last week on the 7-story, 45-unit, 49,244 GSF Cayuga Place Residences project from Bloomfield/Schon + Partners out of Cincinnati, Ohio.  The scaffolding for the block wall construction and ledger boards was taken off-site, and steel columns and beams have arrived with a telescoping boom crane and lift to hoist and tie-in the connections. The 16 columns currently set extend to the 5th floor level, and are topped-off with joining plates to secure framing for the remaining floors.

Constructed is being completed by Turnbull-Wahlert Construction.

Photos from August 14th:

Cayuga_Place-Residences-Ithaca-081414-24

Photos from August 20th:

Cayuga_Place_Residences_08201412

Cayuga_Place_Residences_08201410

Cayuga_Place_Residences_08201404

Cayuga_Place_Residences_08201401

140 College Ave Begins Work

August 18, 2014 // by Jason Henderson

Demo and excavation work on Po Family Realty’s 12-bedroom 140 College Ave has begun: the exterior exit stairway has been disassembled and taken off-site, and a section of the existing one-story structure beside the porch is being demo’ed to prepare for site work and eventual foundations for a 3,800 square foot 12-bedroom expansion, designed by Architect Jason Demarest. The plan dates back a few years, but only proceeded through site plan review a few months ago due to the Collegetown re-zoning, which allows for no minimum parking requirement in CR-4 zones.

140-College-Ave-Ithaca-0814141

140-College-Ave-Ithaca-081414-22

Earlier in June:

140-College-Ave-Ithaca-0615142

The Plans:

140-college-ave-1

140-college-ave-2

CR-4 Lot & Siting Zoning:

Collegetown Form Districts Jan 2014 Draft (dragged)

Thurston Avenue Apartments Wrapping-Up

August 16, 2014 // by Jason Henderson

Thurston Ave Apartments InventoryLots of progress at this site since a week ago: landscaping work has begun, rock base for the driveway and parking lot has been spread, the exterior facades are coming along, the sidewalks have been poured along the street, drive lane, and to each building, and pole lamps have been installed for exterior lighting. The project is aimed at student housing, and the leasing sign for the three buildings indicated August start dates before the semester begins, so I’d imagine this weekend and next week is the rush to finish.

Construction by GM Crisalli & Associates, design by HOLT, landscape architecture by TWMLA, and the project is developed and owned by RABCO Highland House, the same company that owns the apartment building next door.

Thurston-Ave-Apartments-IthacaBuilds-08141403

Thurston-Ave-Apartments-IthacaBuilds-08141408

Thurston-Ave-Apartments-IthacaBuilds-08141409

Thurston-Ave-Apartments-IthacaBuilds-08141406

Thurston-Ave-Apartments-IthacaBuilds-08141401

312-Thurston-Avenue---Drawings-and-Specs

Cayuga Place Residences: Updated Photos for Early August

August 11, 2014 // by Jason Henderson

The 7-story, 45-unit, 49,244 GSF Cayuga Place Residences project from Bloomfield/Schon + Partners being constructed by Turnbull-Wahlert Construction out of Cincinnati, Ohio has completed the core section of block walls, and the scaffolding was on its way back down on August 5th (when these were taken) to install steel ledger boards for the floor framing and other prep-framing work before the two stairs and elevator start to be assembled. There’s an additional parallel block wall, which will likely be assembled as steel framing makes its way up each level with framing fastened between the core and block wall. Construction has taken a brisk pace, as the supporting foundation work began early May, and finished-up later on in June, then block work began late June/early July.

Bloomfield/Schon + Partners is also set to take on a large $20-30 million industrial-reuse project in Cincinnati, at the site of the former Peters Cartridge Factory (14-acre, 250,000 square foot). The plan is to clean-up the site, keep the structure, and build-out 100 loft-style apartments.

Cayuga-Place-Two-2_Ithaca_08051411

Cayuga-Place-Two-2_Ithaca_08051408

Cayuga-Place-Two-2_Ithaca_08051401

Cayuga-Place-Two_Ithaca_0805141

Cayuga_Place_2_Shot

Cayuga Place Residences Units

Thurston Ave Apartments August Photo Update

August 8, 2014 // by Jason Henderson

Photo update here for RABCO‘s 18-unit Thurston Ave Apartments project in Cornell Heights (taken August 3rd and 6th). The exterior facade is shaping-up, as Hardie Stucco Panels and Hardie Trim boards make their way up the three buildings, along with roof fascia boards and soffit panels at the roof edge. The curbing for the parking lot has been set, and looks ready for pouring stone base, then asphalt. The leasing indicated August start dates, so this project should be wrapped-up in the next two weeks to allow for student occupancy for this Fall semester.

Thurston-Ave-Apartments-Ithaca-08061405

Thurston_Ave_Apartments_Ithaca_0703147

Thurston-Ave-Apartments-Ithaca-08061401

Thurston-Ave-Apartments-Ithaca-08061412

Thurston-Ave-Apartments-Ithaca-08061403

Chain Works District August Meeting

August 5, 2014 // by Jason Henderson

07_11_14_Chain_Works_PUD_Application_and_Attachments_Page_14

Unchained Properties and the project team for the 95-acre Chain Works District (former Emerson site) held a second public meeting today (August 5th), primarily to discuss their approach to zoning and to give more information on proposed site layout. Mayor Myrick began the meeting by noting that the community involvement this early-on in a project bodes well for its development, and that the local economy is seeing some of the best numbers statewide as far as unemployment, job growth, and housing creation, so this project will inevitably become a major part of the change we should continue to see in the City.

Myrick and the project team explained the reasoning behind the developer’s decision to seek a Planned Development Zone (PDZ) in the Town of Ithaca, and a Planned Unit Development (PUD) in the City of Ithaca, since the parcel is split between City and Town. The PDZ and PUD are essentially the same thing: it’s a form of zoning and regulatory process that can be approved by the municipality in order to allow a project to develop outside of the current zoning on a parcel or set of parcels.

Scott Whitham of Whitham Planning and Design observed that since the current zoning for the Emerson parcel is Industrial, it would not be applicable or realistic to a large mixed-use redevelopment, as is being proposed, so the project team is submitting zoning materials to both the City and Town to consider in their PDZ and PUD processes, which carry the same requirements as a rezoning of any other area: the community has input and commentary in public meetings throughout the process, and the rezoning would fall under the requirements of the New York State Environmental Quality Review Act (SEQR), and review from the Tompkins County Planning Board. Once the zoning portion is complete, then the project team may submit Site Plan Review applications to the corresponding Planning Boards.

07_11_14_Chain_Works_PUD_Application_and_Attachments_Page_19

Craig Jensen of Chaintreuil | Jensen | Stark Architects summarized some items from the previous presentation: several buildings would likely be demolished to create open spaces between mixed-uses, and the design team is studying similar projects that have incorporated adaptive reuse practices on former industrial sites. The 1/2 mile distance to downtown (closer than Collegetown) will make non-automotive transportation options an attractive prospect.

Chain-Works-Model-City-Town-0805141

07_11_14_Chain_Works_PUD_Application_and_Attachments_Page_28

In addition to working on the zoning proposal for this site, Noah Demarest of Stream Collaborative is working on combining the two Town and City Zoning Codes to conform with the Town Zoning & Comprehensive Plan and the forthcoming City of Ithaca Comprehensive Plan. The combination would be adapted into a Form-Based Zoning Code, with Transect Zones rather than the existing zones and codes we have today, which can be over-complicated and use-based, and contain more amended content than original content.

Transect and Form-based zoning seeks to establish allowable building massing as a priority over accepted uses, and emphasizes a logical transition from rural areas to urban centers, mimicking the transitions found in natural geography. More information is available from the Form-Based Codes Institute and the Center for Applied Transect Studies (which was founded by Andrés Duany and Elizabeth Plater-Zyberk, who wrote the first form-based code for the town of Seaside, Florida). The zoning code suggested here is adapted from SmartCode template, which is a Transect-based subset of form-based codes.

Chain-Works-Zoning-City-Town-0805141

Transectv10_NEW_MedRes_3

Transect-Based Zones are as follows: T1 (Natural) included in project, T2 (Rural) not included, T3 (Neighborhood Edge Zone) not included, T4 (Neighborhood General Zone) included in project, T5 (Neighborhood Center Zone) included in project, T6 (Central Business District Zone) not included.

The existing topography affects these zone decisions: a 15% or greater slope is not realistically developable, so there are several areas, especially towards the south end of the site that would not be developed.
07_11_14_Chain_Works_PUD_Application_and_Attachments_Page_24

07_11_14_Chain_Works_PUD_Application_and_Attachments_Page_25

The question and answer session brought-up traffic concerns on surrounding streets. The Project Team has employed Steve Ferranti of SRF Associates to study the current and historic traffic and transportation patterns, along with trip generation estimates based on the proposal as part of the SEQR process. The team noted that mixed-use projects generally have different peak patterns than single-use, which should help with congestion. Concerns about environmental remediation and removal needs surfaced, which will be studied in detail by the team’s environmental consultant LaBella Associates throughout the same SEQR process, in both rezoning and site plan review. The response from the public was again, quite positive overall.