Photo update here for RABCO‘s 18-unit Thurston Ave Apartments project in Cornell Heights (taken August 3rd and 6th). The exterior facade is shaping-up, as Hardie Stucco Panels and Hardie Trim boards make their way up the three buildings, along with roof fascia boards and soffit panels at the roof edge. The curbing for the parking lot has been set, and looks ready for pouring stone base, then asphalt. The leasing indicated August start dates, so this project should be wrapped-up in the next two weeks to allow for student occupancy for this Fall semester.
Thurston Ave Apartments August Photo Update
August 8, 2014 // by Jason Henderson