Thurston Avenue Apartments Final Building Photos

September 6, 2014 // by Jason Henderson

The three building, three story, 57 bedroom, 18 unit Thurston Avenue Apartments project in Cornell Heights has been completed for occupancy just in time for the start of the semester. Below are some final photos, and a brief project narrative:

The project site plan was approved by the City of Ithaca Planning Board last June, 2013. The structure foundations were dug back in December, with some foundation work over the winter, and then insulated concrete form (ICF) block foundation walls in February. The unusually prolonged and severe winter prevented a lot of early site work (i.e. underground plumbing), but by March, light wood framing for the three-story structures began (framing by Compass Builders), and showed good progress throughout April and May. Roofing started-up and finished in May, and by June, the Marvin windows had been fully installed. Brick veneer base and stone caps began installation in June, and finished by July. Throughout July and August, the façade Hardie stucco panels, side and window trim, roof fascia, and other exterior building finishes were installed, along with landscaping: the project contains a parking lot with 19 parking spaces, concrete curbing and sidewalks, several stone retaining walls along the sloped hillside facing the Thurston Ave/Highland Ave intersection, and ample trees and shrubs. Some landscaping work still remains around the hillside, but certificates of occupancy have been completed, and folks have moved-in.

The project is owned and developed by RABCO Highland House, the operator/owner of the adjacent apartment building, Highland House. Construction was completed by G.M. Crisalli & Associates out of Syracuse, NY, with design by HOLT Architects, and landscape architecture by Trowbridge Wolf Michaels Landscape Architects.

Thurston-Ave-Apartments_09011411

Thurston Ave Apartments Inventory

Thurston-Ave-Apartments_09011409

Thurston-Ave-Apartments_09011407

Thurston-Ave-Apartments_09011404

Thurston-Ave-Apartments_09011410

Thurston-Ave-Apartments_09011405

Thurston-Ave-Apartments_09011416

Thurston-Ave-Apartments-Birdeye

Three-Bedroom-Thurston-Ave

Thurston Avenue Apartments August 20th Photos

August 23, 2014 // by Jason Henderson

RABCO Highland House‘s 18-unit Thurston Avenue Apartments project looks to be wrapping-up just in time for the start of classes. There’s still a bit of facade work to be completed, but the units look complete from the outside. In the space of six days since last post (August 14th to the 20th, when these photos were taken), the driveway and parking lot has been asphalted and striped, all facade and roof fascia panels have been hung on the corner buildings, and the center building’s street-facing facade has been completed, but the sides are missing a few small sections of stucco panelling, which may be done by the time of writing. The site should be seeded and strawed or turfed any day now. The project got a late start (like many) due to the prolonged and intense winter- photos from March.

The construction was done by GM Crisalli & Associates, and designed by HOLT Architects, with landscape architecture by TWMLA.

Thurston-Ave-Apartments_08201406

Thurston-Ave-Apartments_08201407

Thurston-Ave-Apartments_08201410

Thurston-Ave-Apartments_08201414

Thurston-Ave-Apartments_08201415

Three-Bedroom-Thurston-Ave

Thurston-Ave-Apartments-Birdeye

Thurston Avenue Apartments Wrapping-Up

August 16, 2014 // by Jason Henderson

Thurston Ave Apartments InventoryLots of progress at this site since a week ago: landscaping work has begun, rock base for the driveway and parking lot has been spread, the exterior facades are coming along, the sidewalks have been poured along the street, drive lane, and to each building, and pole lamps have been installed for exterior lighting. The project is aimed at student housing, and the leasing sign for the three buildings indicated August start dates before the semester begins, so I’d imagine this weekend and next week is the rush to finish.

Construction by GM Crisalli & Associates, design by HOLT, landscape architecture by TWMLA, and the project is developed and owned by RABCO Highland House, the same company that owns the apartment building next door.

Thurston-Ave-Apartments-IthacaBuilds-08141403

Thurston-Ave-Apartments-IthacaBuilds-08141408

Thurston-Ave-Apartments-IthacaBuilds-08141409

Thurston-Ave-Apartments-IthacaBuilds-08141406

Thurston-Ave-Apartments-IthacaBuilds-08141401

312-Thurston-Avenue---Drawings-and-Specs

Thurston Ave Apartments August Photo Update

August 8, 2014 // by Jason Henderson

Photo update here for RABCO‘s 18-unit Thurston Ave Apartments project in Cornell Heights (taken August 3rd and 6th). The exterior facade is shaping-up, as Hardie Stucco Panels and Hardie Trim boards make their way up the three buildings, along with roof fascia boards and soffit panels at the roof edge. The curbing for the parking lot has been set, and looks ready for pouring stone base, then asphalt. The leasing indicated August start dates, so this project should be wrapped-up in the next two weeks to allow for student occupancy for this Fall semester.

Thurston-Ave-Apartments-Ithaca-08061405

Thurston_Ave_Apartments_Ithaca_0703147

Thurston-Ave-Apartments-Ithaca-08061401

Thurston-Ave-Apartments-Ithaca-08061412

Thurston-Ave-Apartments-Ithaca-08061403

Thurston Avenue Apartments July Photo Update

July 24, 2014 // by Jason Henderson

Thurston Ave Apartments Inventory

RABCO‘s 18-unit, 57-bedroom Thurston Avenue Apartments project is showing completed brick facade work, sitework to prep for a new parking lot and driveway, some landscaping stonework, and the HardieTrim panels and synthetic stucco is coming along on Buildings C & D. The Marvin Integrity windows were installed back in June, and the buildings were fully-framed, wrapped, and roofed throughout the month of May.

The project is being built by G.M. Crisalli & Associates, with design by HOLT Architects, and landscape by TWLA.  Occupancy is expected in August, for students moving-in to begin the Fall semester.

 

July 24th:
Thurston-Ave-Apartments-Ithaca-06241401

Building C:
Thurston-Ave-Apartments-Ithaca-06241410

Thurston-Ave-Apartments-Ithaca-06241404

Building D:
Thurston-Ave-Apartments-Ithaca-06241412

Site Plan below (Building A, the small one in the corner will be a later phase):

Thurston-Ave-Apartments-Birdeye

July 2nd:

Thurston-Ave-Apartments-Ithaca-07021409

Thurston-Ave-Apartments-Ithaca-07021406

Thurston Ave Apartments May Photo Update

May 20, 2014 // by Jason Henderson

With a target opening date of August, progress on RABCO Highland House‘s Thurston Avenue Apartments project has advanced along, with envelope framing completion on Buildings C & D and only a small section of tar paper and roofing tiles needed to complete the roof installation on Building D, as the other two buildings have been finished.

The base sections of brick facade were laid last month, and the rest of the facade will consist of a combination of Hardie trim boards, textured synthetic stucco (EIFS) finished in several different colors, and Hardie soffit panels. The windows and doors were reviewed by the Ithaca Landmarks Preservation Commission late last year due to Cornell Heights Historic District considerations, and will include Integrity fiberglass grilled double hung windows, and Marvin commercial doors finished to match the facade colors.

 
Thurston_Ave_Apartments_Ithaca_05191411

Thurston_Ave_Apartments_Ithaca_05191414

Thurston_Ave_Apartments_Ithaca_05191416

Thurston_Ave_Apartments_Ithaca_05191402

Thurston_Ave_Apartments_Ithaca_05191405

Thurston-Avenue-Apartments---SPR-Revised-Drawings---05-28-132

312-Thurston-Avenue---Drawings-and-Specs