RABCO Highland House‘s 57-bedroom Thurston Avenue Apartments project has had complete roofing for weeks now, and almost all of the double-hung grilled Marvin windows have now been installed in the rough openings. By now interior framing is complete, the electric, plumbing, sprinklers and fixtures are in the rough-ins phase, and drywall, paint, and flooring should follow along afterwards. The exterior already has brick veneer base, which will transition to Hardie boards and synthetic stucco the rest of the way up. The exterior facade and paving/curbing should go quickly, since the buildings are leased for August occupancy. The site design is by Trowbridge Wolf Michaels Landscape Architects, with architecture by HOLT, and construction managed by G.M. Crisalli & Associates.
Thurston Avenue Apartments June Photo Update
June 16, 2014 // by Jason Henderson