Klarman Hall Structural Steel Complete

April 7, 2015 // by Jason Henderson

Hats off to Welliver and the crew from Raulli & Sons Ironworks sticking it out through the winter to get the structural steel done. Steel crane is now off site, and as the project rolls on, the new folding jib telescopic tower crane is up-and-running for the remainder of the work, especially the Josef Gartner glass installers that will be working on the glazed ceiling and wall systems that compose the atrium structure.

Throughout the structural phase, many of the exterior wall frames have now been assembled and sheathed with glass-mat sheathing in preparation for sandstone panels and various cladding types, and trades for electrical, plumbing, sprinkler systems, etc. have been busy. Interior framing started on the North side in March, and drywall and paint will be taking up much of May and June.

Photos from April 6th:
Klarman-Hall-Cornell-040615 - 3

Klarman-Hall-Cornell-040615 - 2 (1)

Klarman-Hall-Cornell-040615 - 1

Photos from March 10th:

Klarman_Hall-Cornell_Ithaca_031015 - 2

Klarman_Hall-Cornell_Ithaca_031015 - 3

klarman-atrium

Cornell_Klarman_Hall_Render

Lofts@SixMileCreek Construction Photos

April 1, 2015 // by Jason Henderson

Steve Bloomfield of Bloomfield/Schon + Partners was kind enough to grant a tour of his Lofts@SixMileCreek project downtown, so here are some photos taken about two weeks ago, and the press release from yesterday. The construction schedule has been revised for late summer completion, but a tour will be available April 18th through the Downtown Ithaca Alliance. Most walls have been framed, and trades are currently roughing-in services at the top floors, and drywall and finish-work has begun at the lower floors. The exterior wall framing and glazing has progressed to the fifth floor, so the building should be almost fully-enclosed in the coming weeks.

The project is a 7-story, 49,244 square foot structure that will contain 45 rental apartment units. The building is being developed by Bloomfield/Schon + Partners, with construction by Turnbull-Wahlert Construction.

Unit floor layouts link here

Lofts@SixMileCreek_Ithaca_031415 - 1

Press Release March 31 2015 Final - Online Leasing

Photos taken March 14th, 2015:

Lofts@SixMileCreek_Ithaca_031415 - 2

Lofts@SixMileCreek_Ithaca_031415 - 14

Lofts@SixMileCreek_Ithaca_031415 - 22

Lofts@SixMileCreek_Ithaca_031415 - 15

Lofts@SixMileCreek_Ithaca_031415 - 9

Simplex Modular Factory Tour

March 17, 2015 // by Jason Henderson

I ventured down to Scranton, Pennsylvania for a factory open house tour at the Simplex Homes production facility a couple weekends ago, and thought I’d share some photos here. Simplex produces modular units for builders putting together everything from single-family homes, to townhouses, four-story apartment complexes, and student dormitories. Modular construction is essentially just a construction technology that can be applied to many different structures and situations. Simplex specializes in wood-framed units with a surprisingly-complete level of finish already done before trucking and craning on-site. In addition to production efficiency, factory-settings tend to ensure better QC, material recycling, and environmental control.

Their production is most notable in the Ithaca area for Belle Sherman Cottages, an East Hill 19 single-family detached and 10-townhome project developed by Agora Development and built by Carina Construction. Project page and photos here.

When visiting, the crews were working on a ~300 box project for a four-story multifamily development for downtown Philadelphia.

Simplex-Scranton-Tour01

Simplex-Scranton-Tour02

Simplex-Scranton-Tour03

Simplex-Scranton-Tour04

Simplex-Scranton-Tour05

Simplex-Scranton-Tour06

Simplex-Scranton-Tour07

Simplex-Scranton-Tour08

Simplex-Scranton-Tour09

Simplex-Scranton-Tour10

Simplex-Scranton-Tour11

Simplex-Scranton-Tour12

Simplex-Scranton-Tour13

Simplex-Scranton-Tour14

Simplex-Scranton-Tour15

Simplex-Scranton-Tour16

Simplex-Scranton-Tour17

Simplex-Scranton-Tour18

Simplex-Scranton-Tour19

Simplex-Scranton-Tour20

Simplex-Scranton-Tour21

Simplex-Scranton-Tour22

Simplex-Scranton-Tour23

Simplex-Scranton-Tour24

Simplex-Scranton-Tour25

Simplex-Scranton-Tour26

Simplex-Scranton-Tour27

Simplex-Scranton-Tour28

Simplex-Scranton-Tour29

Simplex-Scranton-Tour30

Simplex-Scranton-Tour31

Simplex-Scranton-Tour32

Simplex-Scranton-Tour33

Purity Ice Cream Phase II Photo Update

March 16, 2015 // by Jason Henderson

Long overdue photos here, but the Phase II section of the Purity Ice Cream project was completed back in late January, and here are some photos of the new space. The expanded seating area greatly increases interior seating in the renovated rooms formerly used for kitchen and dairy processing, and work is currently underway on Phase III: renovating the former storage area in the west side of the building into retail and business operations. Stop-in and check it out: Pancake Saturdays and Sundays launch March 28th!

The project was designed by John Snyder Architects, and work completed by Strawbridge and Jahn Builders, along with specialty trades from the area.

Purity_Ice_Cream_Ithaca_030315 - 13

Purity_Ice_Cream_Ithaca_030315 - 8

Purity_Ice_Cream_Ithaca_030315 - 11

Purity-Ice-Cream-Plans_Ithaca_031415 - 1

Purity_Ice_Cream_Ithaca_030315 - 3

Purity-Ice-Cream-Plans_Ithaca_031415 - 2
 

New glass canopy added to the main entrance:

Purity_Ice_Cream_Ithaca_031315 - 1

Cornell’s Klarman Hall Project Finishing Structural Steel

March 1, 2015 // by Jason Henderson

Welliver has been working away on Cornell’s 33,250 square-foot Klarman Hall Project throughout this winter, and in the next week or so, should be complete with all structural steel components. The construction has been split between the south and north sections in each phase since starting the enabling work in September 2013 and pursuant foundation excavation and foundation footings in July 2014. The two sections contain classrooms, offices, and the north section a 350-seat auditorium, and are joined by a large interior atrium, utilizing the rotunda of Goldwin-Smith Hall for seating, food/cafe counter service, and ingress/egress. Klarman and Goldwin-Smith will be combined through several connecting hallways and common areas as well, as shown in the plans below.

Since October, the structural steel contractor Raulli & Sons Ironworkers out of Syracuse have been delivering, craning, bolting, and welding the steel columns and beams into place, along with the massive atrium trusses that stretch the two main structural sections. As steel finished-up on the south section late November, crews moved-in to deck the floors with corrugated sheet metal and applied steel mesh to reinforce the concrete floor pours. Once the concrete dried in January, framers came in to frame the walls with steel studs and sheetrock the walls. According to the schedule (end of post), Josef Gartner comes on-site to mobilize this march to install the glass atrium. Once the large hoist crane for the steel is off-site, and the lane is cleared of equipment, East Ave will be opened-up to two-way traffic again by April 20th.

Speciality trades, framing, and drywall will take-up much activity on both the South and North Sections until June/July, and by the Fall, painting, building systems, and finish-work will be left to tackle. The project is slated for a December 2015 delivery.

 
Photos taken February 27th:

Klarman-Hall-Cornell-Welliver-02271504

Klarman-Hall-Cornell-Welliver-02271507

Klarman-Hall-Cornell-Welliver-02271520

Floor Plans:
klarman-hall-floor-plans-1

klarman-hall-floor-plans-2

klarman-atrium

 
Photos taken January 4th:
Klarman-Hall-Cornell-0104152

Klarman-Hall-Cornell-0104153

 
Photos taken December 14th:

Klarman-Hall-Cornell-1214146

Klarman-Hall-Cornell-1214145

Klarman-Hall-Cornell-1214141

 
Photos taken November 24th:

Klarman-Hall-Cornell-11241413

Klarman-Hall-Cornell-11241408

Klarman-Hall-Cornell-11241401

 
Photos taken November 3rd:

Klarman-Hall-Ithaca-11031405

 
Photos taken October 14th:
Klarman-Hall-Cornell-1014142

Klarman-Hall-Cornell-1014147
Klarman-Hall-Cornell-1014146

Cornell_Klarman_Hall_Render

2015-Klarman-Hall-Construction-Schedule-2

Marriott Project Digs and Drives Shoring Beams

February 26, 2015 // by Jason Henderson

William H. Lane Construction has been working away at the future 159-room, 10-story Downtown Marriott project since receiving notice to proceed last September from Developer Urgo Hotels. Partners in the project include Rimland Development and Ensemble Investments. A large crane is now on site, and a bulldozer and excavator have been digging out the small parcel’s hillside. The shoring beams along the South Aurora Street side will be used to support a shoring wall due to the need to excavate the site to start the foundation. A generator on site runs the electrical equipment, and part of the early sitework involved the relocation of electric utility services around the corner on Green Street (the site contained a small underground NYSEG substation).

The total development cost is pegged at $32 million, with a completion target of 2017. The project is designed by Cooper Carry Architects based in Atlanta, with offices out of Alexandria, VA and New York City.

Photos from February 24th:
Marriott-Downtown-0224154

Marriott-Downtown-0224152

Marriott-Downtown-Ithaca-022415-203

Marriott-Downtown-Ithaca-022415-202

Marriott-Downtown-Ithaca-022415-204

Marriott-Ithaca-3

Marriott-Ithaca-7

Lofts@SixMileCreek November to February

February 26, 2015 // by Jason Henderson

November to February photo updates here for the downtown Ithaca Lofts@SixMileCreek project, building a 7-story, 49,244 square foot structure that will contain 45 rental apartment units. The building is being developed by Bloomfield/Schon + Partners, with construction by Turnbull-Wahlert Construction.

The structure was furred-out with lumber on the edges and wrapped in plastic in November to prepare for the arctic winter we’ve been experiencing here in Ithaca, and work has since sped-away to finished wall-framing, rough plumbing, electric, HVAC, exterior sheathing, exterior wall systems (windows and conventional metal framing) and interior wallboard. The phasing for each trade has progressed from the first floor and up, so it’s likely that the lower stories are in the midst of finish-work. The shower stalls made their way in during the early wall-framing phase in October (most units secure directly to studs nowadays).

The structure topped-out on October 2nd with a press event and completion is scheduled for Spring 2015, probably May.

Project Website has launched: http://ithacalofts.com/

Photos from February 24th, 2014:
Lofts@SixMileCreek-Ithaca-0224152

Lofts@SixMileCreek-Ithaca-0224154

 
Photos from November 24th, 2014:
Lofts@SixMileCreek-Ithaca-11241419
Lofts@SixMileCreek-Ithaca-11241410

 
Photos from November 3rd, 2014:
Lofts@SixMileCreek-Ithaca-11031412
Lofts@SixMileCreek-Ithaca-11031411

Downtown Marriott Project Selects General Contractor

October 28, 2014 // by Jason Henderson

Binghamton-based William H. Lane Inc. General Contractors has been selected to lead the construction for the downtown Ithaca Marriott project, which should be breaking ground later this year. The project is being developed by Urgo Hotels, a group out of Bethesda, Maryland with over 30 hotels under management.

The Marriott will be a 159-room, 10-story hotel with a restaurant/bar on the lobby level designed by Cooper Carry. The total development cost was pegged at $32 million, and is scheduled for spring 2017 completion.

Below are the updated renders and site plan review materials, reflecting the final designs and materials for the project:

Marriott-Ithaca-3

Marriott-Ithaca
Marriott-Ithaca-7
Marriott-Ithaca-6
Marriott-Ithaca-5

Marriott-Ithaca-4
Marriott-Ithaca-2

Lofts@SixMileCreek October Photo Update

October 28, 2014 // by Jason Henderson

Photo updates here for the downtown Ithaca Lofts@SixMileCreek project, building a 7-story, 49,244 square foot structure that will contain 45 rental apartment units. The building is being developed by Bloomfield/Schon + Partners, with construction by Turnbull-Wahlert Construction.

The sprinkler pipe-fitters have made their way from the ground floor to 5th, and interior metal stud walls were roughed-in on the ground through the third floor with bottom plate layouts installed on the fourth as of late last week. Shower stalls have made their way into more than a dozen bathrooms, as plumbing risers and pipes are fitted alongside wall completions. A paint contractor has been spraying down the structural steel with fire retardant intumescent paint (the white coating). The structure topped-out on October 2nd with a press event and completion is scheduled for early 2015.

Photos from October 17th:
LoftsatSixMileCreek-10-17-1416

LoftsatSixMileCreek-10-17-1412

Photos from October 24th:
Lofts@SixMileCreek-10241412

Lofts@SixMileCreek-10241410
Lofts@SixMileCreek-10241405
Lofts@SixMileCreek-10241402

Statler Hall Entry Renovation Project Complete

October 26, 2014 // by Jason Henderson

The Statler Hall Entry Renovation has been opened-up since late August, but the interior work and all exterior finishes are now complete. Here are some final photos for the project, which began in early summer, and took out the western-facing 1987 arched limestone entryway to replace with a new limestone and glass-wrapped 450 square foot vestibule and expanded space on the second floor above. Photos throughout construction may be seen on the project category page.

General contracting services by Northland Associates out of Syracuse, NY, and design by KSS Architects out of Princeton, NJ, and M/E Engineering out of Syracuse, NY.

Photos from September 21st:
Statler-Hall-Cornell-0921147

Statler-Hall-Cornell-0921141

Photos from October 15th:
Statler-Hall-Entry-Cornell-1014141
Statler-Hall-Entry-Cornell-1014143

Photos from October 24th:
Statler-Entry-Cornell-1024141
Statler-Entry-Cornell-1024146
Statler-Entry-Cornell-1024145

Before:
Statler_Hall_Entry_1225133

Design Render:
Statler-Hall-Entry-Renovation-Render