Steel Erectors at Work on Klarman Hall

October 8, 2014 // by Jason Henderson

Cornell’s future 33,250 square foot Klarman Hall project being built by Welliver has finished-up the north and south foundations, and steel erectors are on site craning and bolting steel columns and beams in place on the south end. The columns are anchored to each foundation footing cap or pier, then the beams between each column are bolted and welded to the proper connection. The north end’s steel work should be completed by early November, and we’ll see the atrium steel assembly commence and complete throughout November.

Photos from September 29th:
Klarman-Hall-Cornell-9291408

Klarman-Hall-Cornell-9291404

Photos from October 5th:
Klarman-Hall-Cornell-1005146

Klarman-Hall-Cornell-1005143

Klarman-Hall-Cornell-1005147