Statler Hall Entry Renovation Project Complete

October 26, 2014 // by Jason Henderson

The Statler Hall Entry Renovation has been opened-up since late August, but the interior work and all exterior finishes are now complete. Here are some final photos for the project, which began in early summer, and took out the western-facing 1987 arched limestone entryway to replace with a new limestone and glass-wrapped 450 square foot vestibule and expanded space on the second floor above. Photos throughout construction may be seen on the project category page.

General contracting services by Northland Associates out of Syracuse, NY, and design by KSS Architects out of Princeton, NJ, and M/E Engineering out of Syracuse, NY.

Photos from September 21st:
Statler-Hall-Cornell-0921147

Statler-Hall-Cornell-0921141

Photos from October 15th:
Statler-Hall-Entry-Cornell-1014141
Statler-Hall-Entry-Cornell-1014143

Photos from October 24th:
Statler-Entry-Cornell-1024141
Statler-Entry-Cornell-1024146
Statler-Entry-Cornell-1024145

Before:
Statler_Hall_Entry_1225133

Design Render:
Statler-Hall-Entry-Renovation-Render

Statler Hall Entry Renovation Nearing Completion

September 16, 2014 // by Jason Henderson

Cornell’s $2.4 million Statler Hall Entry Renovation project seems to be nearing completion: the exterior limestone veneer facade sections are installed, and the second floor interior ductwork and mechanicals have been wrapped in insulation. Next up are final touches to the exterior- aluminum trim work between the glass curtain wall, roof fascia, stone base sill, bike racks, and the remainder of the interior finishes.

The design is by KSS Architects and M/E Engineering, and the project has been managed in-house by Cornell Facilities Services.
The renovation is intended to match the additions that have been completed on the eastern and southern sides: the Beck Center along the eastern side (Phase One Expansion), and the renovated auditorium tower on the southern side (Phase Two expansion). KSS Architects designed both the Beck Center and the Tower Renovation

Photos from September 1st:
Statler-Hall-Entry-Cornell_0901148
Statler-Hall-Entry-Cornell_0901147

Photos from September 7th:
Statler-Hall-Entry-0907145

Photos from September 15th:
Statler-Entry-Cornell-Ithaca-0916146
Statler-Entry-Cornell-Ithaca-0916143
Statler-Entry-Cornell-Ithaca-0916142

Before Photo:
Statler_Hall_Entry_1225133