Structural steel assembly began last week on the 7-story, 45-unit, 49,244 GSF Cayuga Place Residences project from Bloomfield/Schon + Partners out of Cincinnati, Ohio. The scaffolding for the block wall construction and ledger boards was taken off-site, and steel columns and beams have arrived with a telescoping boom crane and lift to hoist and tie-in the connections. The 16 columns currently set extend to the 5th floor level, and are topped-off with joining plates to secure framing for the remaining floors.
Constructed is being completed by Turnbull-Wahlert Construction.