Ithaca Builds

Mapping, photos and information for Ithaca construction and development projects

TC3’s Coltivare Space Plumbing and Framing Work

May 21, 2014 // by Jason Henderson

TC3_Coltivare_Ithaca_0519144

Tompkins Cortland Community College‘s 17,000 square foot Coltivare space inside the ground floor of the Cayuga Street Garage has been moving along with a ton of below-slab plumbing work, and metal stud wall framing. Cuts made into the concrete floor slab have been jackhammered out, dug, and pipes laid by HALCO Plumbing & Heating for a slew of drains that will serve bar, prep, kitchen, classroom, and restroom sinks and toilets.

Due to the downward sloping ceiling deck in the back half of the space from south to north, the floor layout utilizes the lower-clearance space for storage, then restrooms, then classroom space towards the southeast. The southwest to center-west portion will comprise the public restaurant, along with ample outside seating along the corner and following East Clinton Street. The plan is to be ready and open this August, in time for the Fall semester. The design for the space is by Ramsgard Architectural Design, with general contracting services by Turnbull-Wahlert. Along with Coltivare, this corner of Ithaca will be seeing quite a transformation with the addition of the 39-apartment unit Cayuga Place Residences over the course of the next year.

There’s a new online video from TC3 explaining the Farm to Bistro program, containing interviews from locals in the food and wine industry:

 

TC3_Coltivare_Ithaca_0519147

TC3_Coltivare_Ithaca_0519141

Coltivare-Modified-SPR-Application-Form-and-Drawings---02-18-14-3

Thurston Ave Apartments May Photo Update

May 20, 2014 // by Jason Henderson

With a target opening date of August, progress on RABCO Highland House‘s Thurston Avenue Apartments project has advanced along, with envelope framing completion on Buildings C & D and only a small section of tar paper and roofing tiles needed to complete the roof installation on Building D, as the other two buildings have been finished.

The base sections of brick facade were laid last month, and the rest of the facade will consist of a combination of Hardie trim boards, textured synthetic stucco (EIFS) finished in several different colors, and Hardie soffit panels. The windows and doors were reviewed by the Ithaca Landmarks Preservation Commission late last year due to Cornell Heights Historic District considerations, and will include Integrity fiberglass grilled double hung windows, and Marvin commercial doors finished to match the facade colors.

 
Thurston_Ave_Apartments_Ithaca_05191411

Thurston_Ave_Apartments_Ithaca_05191414

Thurston_Ave_Apartments_Ithaca_05191416

Thurston_Ave_Apartments_Ithaca_05191402

Thurston_Ave_Apartments_Ithaca_05191405

Thurston-Avenue-Apartments---SPR-Revised-Drawings---05-28-132

312-Thurston-Avenue---Drawings-and-Specs

Cayuga Place Residences Foundation Work

May 19, 2014 // by Jason Henderson

The Bloomfield/Schon + Partners‘ 45-unit Cayuga Place Residences project is moving along on foundation work, with a combination of reinforced concrete footings and STELCOR augur grouted steel core displacement piles (the grid of steel tubes with caps sticking out of the ground). I mentioned these in a post back in March; they’re a form of micro-pile whereby the drilling auger goes into the soil, creates displacement, then the reservoir gap is filled with grout, water is poured in for the mixture to cure, then the interior core of the steel auger is filled with grout and stays in the ground. They’re necessary to stabilize the weight of the building in this soil, which is challenging to build on.

The excavation and footings will continue along the footprint of the building, then we should be seeing structural steelwork follow-up to frame the building. There’s also been some sitework for plumbing. The work is being done by Turnbull-Wahlert Construction, the same firm that completed Cayuga Place, the adjacent Cayuga Street Parking Garage, and also the general contractor for TC3’s Coltivare buildout on the ground floor.

Cayuga_Place_Residences_Ithaca_05191403

Cayuga_Place_Residences_Ithaca_05191402

Cayuga_Place_Residences_Ithaca_05191405

Cayuga_Place_Residences_Ithaca_05191404

Cayuga_Place_Residences_Ithaca_05191410

Cayuga_Place_2_Shot

More Photos from May 19th:

Photos from May 8th:

Cornell Klarman & Goldwin Smith Hall Photo Update

May 18, 2014 // by Jason Henderson

An excavator has been removing soil in front of the shoring wall along East Ave, and re-roofing work on Goldwin Smith has progressed to the west side of the building, facing the Arts Quad. I’m not positive, but in looking at the drawings, there must be another shoring wall to go in closer to East Ave. in order to excavate another section of soil for the future building’s foundation. The project schedule shows rock removal beginning about a week from now, so there’s probably a solid layer of bedrock underneath the excavated area. The lowest floor of Klarman Hall will sit nearly equal with Goldwin Smith’s lowest floor, so the excavation will be going down much further.

Klarman Hall will be a new 33,250 square foot Humanities Building, designed by Koetter | Kim & Associates and built by Welliver to be completed around the end of 2015. Goldwin Smith Hall was built in 1892, designed by Charles Osborne (an architecture professor), Carrère and Hastings (a prominent Beaux-Arts/neo-classical architecture firm).

Cornell_Klarman_Goldwin_Hall_Ithaca_05131406

Cornell_Klarman_Goldwin_Hall_Ithaca_05131404

Klarman-sidewalk

Klarman-Hall---Site-Plan-Floor-Plans-Sectional---02-19-13

Cornell_Klarman_Goldwin_Hall_Ithaca_05131403

Cornell_Klarman_Goldwin_Hall_Ithaca_05131401

Klarman-Hall---Presentation---04-24-13

Cornell Law School Renovation Interior Photos

May 15, 2014 // by Jason Henderson

Cornell_Law-School_Addition_Ithaca_05131417

 

I swung inside the Cornell Law School Expansion this past week to follow-up from the last post with interior photos. This expansion wing on Myron Taylor Hall began back in 2012 and finished-up just a couple weeks ago, in time for convocation this weekend. It was designed by Ann Beha Architects, and constructed by Welliver.

The interior certainly kept with the idea of synthesizing a modern addition into an existing historic structure in a very tasteful manner. There are many wooden surfaces and trim work, and the stone is kept exposed on the interior. Nothing seemed to be either too ornate, or too modern. The lighting is relaxing, and the large windows bring a lot of natural light into the hall lounge. The classrooms are nice as well- good visibility from every seat, and additional screens on each side of the central lecterns. Genuinely tempting to hang out here and read a book, just a great, comfortable space:

 

Cornell_Law-School_Addition_Ithaca_05131411

Cornell_Law-School_Addition_Ithaca_05131412

Cornell_Law-School_Addition_Ithaca_05131407

Cornell_Law-School_Addition_Ithaca_05131419

Cornell_Law-School_Addition_Ithaca_05131405

law-school-expansion

Commons Rebuild Update & Phasing

May 14, 2014 // by Jason Henderson

Commons_Rebuild_Ithaca_0513141

The Ithaca Commons Rebuild Project Team gave a presentation this morning on the phasing for this Summer and Fall (Phase 3), as the paving and the bulk of the remaining work wraps up this November. Michael Kuo, the Project Manager has agreed to share slides from the meeting that help to explain the rest of the project.

As was reported in the news and at the meeting, the team was able to value engineer certain portions of the project in order to re-integrate the gateway structures, and playground, which is being designed by Play by Design, a local firm specializing in custom playgrounds that has built hundreds of projects throughout the world. The City of Ithaca has agreed to install the mechanical vault and run plumbing lines for the future water feature, which is expected to attract donor funding to build at a point in the future.

Commons-Gateway-West

In the last six weeks since work resumed in earnest, the telecom mains and services have been run, along with water service upgrades that have involved digging-up and connecting the mains to water, fire sprinkler system lines, and telecom piping into each building (commonly called “laterals”). Once connected, the piping is tested and then the old services disconnected and taken out. The crews have averaged about 2-3 each day.

Commons_Rebuild_Ithaca_0513143

Commons-Rebuild-Ithaca-0414142

Slide2

 

A new electric duct bank is currently being installed by NYSEG, along with a new gas main, replacing the old galvanized steel gas piping with high density polyethylene yellow gas pipe (HDPE), a similar material to plastic bottles actually, but much stronger. After the gas main section is replaced on the 200 Block’s north side, NYSEG will then cut open and replace the lines on the south sides of both blocks, then back around the northern side of the 100 Block from the west.

 

Slide4

Commons_Rebuild_Ithaca_0513142

 

As the underground utilities are completed in each wing of the Commons, the paving program will begin in July, as crews will grade and prep surfaces for pouring a concrete base, on top of which, the concrete surface pavers will be set for the final walkable layer. Because the concrete can be poured section by section, and dry time is relatively fast for concrete, the surfaces will be opened-up to pedestrian traffic, starting with Bank Alley, then the east 200 Block, and west 100 Block.

Per each wing, the concrete base is poured, then pavers set, which should take about 3-4 weeks in each phase
Phase 1: Bank Alley (mid-June to late June)
Phase 2: 200 Block (late July, possibly August)
Phase 3: 100 Block (starting in October)

 

Here’s the phasing for the Bank Alley wing:

Slide5

Slide6

Scenes from the last few weeks:

Commons-Rebuild-Ithaca-0418141

Collegetown Terrace Early May Photo Update

May 12, 2014 // by Jason Henderson

Many of the remaining sections of synthetic stucco have been coated to their final finish along the southern faces of Buildings 5 & 6 since about three weeks ago (hard to believe there was snow on the ground then), and along the roof lines, it looks like some of the metal coping has been installed over top the EPDM membrane edges. When I swung by, there was a crew on the northern side of Building 5 installing the scale-like facade, which has also progressed on Building 6’s northern side. At the entrance between Buildings 5 & 6, there’s also a set of forms for pouring a new retaining wall along Building 5. I haven’t seen the interiors, but there’s no doubt they’re far along, as the extended cold winter provided ample time for focusing on interiors at many project sites in the area. Amenities for the Building 5 units listed here.. granite counters, limestone tile, fully furnished- sounds nice.

These two buildings will be done by the end of summer, in time for the Fall semester. The developer/management company, Novarr-Mackesey has posted a new site map of the project online (embedded below, minus the future Building 7), and the General Contractor, Welliver has also been busy over at Cornell’s Klarman Hall project, which should start foundation work later this summer.

Southern faces of Buildings 5 & 6:
Collegetown_Terrace_Ithaca_05081413

Collegetown_Terrace_Ithaca_05081416

Site Map:
Prop_SiteMap2014

Northern face of Building 5, vinyl facade installation:
Collegetown_Terrace_Ithaca_05081407

Southern face of Building 5 (west end):
Collegetown_Terrace_Ithaca_05081418

West end of Building 6:
Collegetown_Terrace_Ithaca_05081403

East end of Building 5, looks like work for a new retaining wall:
Collegetown_Terrace_Ithaca_05081401

Planned Parenthood Nearly Complete, Interior & Exterior Photos

May 11, 2014 // by Jason Henderson

The Planned Parenthood of the Southern Finger Lakes‘ Ithaca project is nearing completion: the parking lot has been paved with asphalt by Heath Asphalt Paving, the remaining sections of sidewalk and curbing have been poured, construction fence taken down, remaining openings filled with windows, window shades installed, and various other exterior and interior finish work completed by LeChase Construction. The organization hosted an open-house tour of their new facility this past Thursday, May 8th, and here are some photos taken from the exterior and interior. The design was done by Chiang O’Brien Architects.

The interior finishes have nice features like metal-framed clerestory windows above solid-core doors for each exam room, a mix of carpet tiles and linoleum, solid cabinetry and countertops, and a variety of lighting fixtures. The layout on each floor is logical: a rectangular-routed hallway wraps nurse and administrative stations on the first floor, with exam rooms, offices, and the waiting room along the exterior walls. The second floor contains mostly office space, with an additional open waiting area, and a conference room. All in all, it’s a professional-looking project (and much improved space) for a great local organization providing valuable services for the area.

Hard to believe, but five days short of a year ago, the site was a flat plot of dirt and stone when I first took some photos here May 16th, 2013.

Photos from May 8th:
Planned_Parenthood_Ithaca_05081420

Planned_Parenthood_Ithaca_05081418

Planned_Parenthood_Ithaca_05081415

Planned_Parenthood_Ithaca_05081414

Planned_Parenthood_Ithaca_05081408

Planned_Parenthood_Ithaca_05081416

Planned_Parenthood_Ithaca_05081403

April 21st:
Planned_Parenthood_Ithaca_0421141

May 5th:
Planned_Parenthood_Ithaca_0505145

Planned_Parenthood_Ithaca_0505144

Purity Ice Cream Re-Opens

May 9, 2014 // by Jason Henderson

Purity-Logo

Purity Ice Cream has re-opened and their renovated counter, serving area, seating, and bathrooms are ready to go. The side entry should follow-up shortly, and a new canvas awning will be going over the new steel canopy above the outside seating.

The renovations began back in January with some significant interior demolition of the entire serving, seating, and bathroom areas. The electrical, plumbing, and HVAC have all been completely re-done, and the finish work is all new, minus the lovely old menus.

The re-opening comprises the first phase of the project, with the interior demolition and re-furnishing of the old prep and production rooms for a large area of additional interior seating to follow. The back (west) portion of the building will be built-out for commercial tenancy, as the existing building contains ample room for a nice office unit. At this time the roof plans from the initial January plan are undetermined, so there may or may not be areas built-out above.

As the temperatures finally rise to sweat-weather in Ithaca, swing by Purity at the intersection of Meadow St and Cascadilla St and get yourself some ice cream!

The project was designed by John Snyder Architects, and work completed by Strawbridge and Jahn Builders, along with specialty trades from the area.

Purity_Ice_Cream_Ithaca_05081404

Purity_Ice_Cream_Ithaca_05081412

Purity_Ice_Cream_Ithaca_05081411

Purity_Ice_Cream_Ithaca_05081401

Concept Render:
Purity-Render-Jan-10-2014

A couple interior shots from May 21st:
Purity-Ice-Cream-Ithaca-412141

And more from earlier this week:

Westgate Plaza, Finger Lakes Beverage Center Update

May 6, 2014 // by Jason Henderson

The Westgate Plaza containing the Finger Lakes Beverage Center and FedEx Office is currently being re-sided in addition to interior work that, if I’m reading the plans correctly, will result in an expanded mercantile space for the beverage center (entry on the western side, change of occupancy from S-1, storage to M, mercantile). As you can see from the roof, there’s a new layer of EPDM being installed, as submitted in the site plan review application in June last year, and the ceiling structure in southern portion of the building is being modified to accept a new drop ceiling, along with new partition walls and coolers. The renovated exterior will feature a wraparound apron roof, and a redesigned parking lot in addition to new siding.

The work is being done by Benchmark Construction Fitz Contracting LLC out of Trumansburg

Westgate_Plaza_Beverage_Center_Ithaca_0502143

Westgate_Plaza_Beverage_Center_Ithaca_0502141

westgate-plaza-2