A few more windows on the east side of Goldwin Smith Hall have been boarded-up, and roofing work as part of the enabling work scope for the Klarman Hall project has been proceeding (LeChase Construction), as the entire existing slate and metal roofing materials are replaced with new metal, flashing, and slate pieces. If I’m not mistaken, I believe by this point, the entire north wing, the northern-central section, and the southern and northern slopes of the south wing have new slate installed. The Cornell Chronicle posted an article about how the temperatures have been affecting the project.
The target completion for Klarman Hall is late 2015, with 33,250 square feet of new space going for LEED Platinum certification, a 350 seat auditorium, and a large inner-atrium space, opening-up the Goldwin Smith rotunda for cafe-service areas and entry/egress into Goldwin Smith. Embedded images for each of the four floor plan levels are here in the previous post. Welliver is the general contractor on this project.