State & Mitchell Intersection Lighting

January 5, 2014 // by Jason Henderson

The crossing lights and automobile signalling lights have been installed on each of the poles, but the signalling sequences have yet to be programmed, and thus, the intersection is still an all-way stop- however, both lanes heading into the City on Mitchell Street have been opened-up for a few weeks now. The project contract sum is $342,677, awarded to Binghamton Road Electric, LLC (Bothar Construction), out of Binghamton, NY. $150,000 of the cost is being paid for by Cornell University, through the Cornell/Community Transportation Initiative.

State_and_Mitchell_1225131