Ithaca Builds

Mapping, photos and information for Ithaca construction and development projects

Planned Parenthood, Definitely Not Slowing Down

October 2, 2013 // by Jason Henderson

Planned Parenthood of the Southern Finger Lakes’ project has way more structural steel up (basically the whole building envelope), as well as corrugated steel decking for floors and roof sheathing. The north-west steel stair ramp is making its way around the concrete elevator tower that was poured just a few weeks ago. I haven’t been able to swing by during the day to see what kind of crew they’ve got, but the gross majority of this steel framing work has been completed in about two weeks flat. Pretty impressive stuff.

Planned_Parenthood_10101

Planned_Parenthood_10104

Planned_Parenthood_10105

Planned-Parenthood-Orthos

Press Bay Alley Demolition Prep for Steel

October 1, 2013 // by Jason Henderson

Press Bay Alley’s old garage doors have been completely removed in preparation for Accufab‘s steel work on each of these bays for micro-retail spaces. Accufab’s work will be going on this week, and then Overhead Door will be installing new roll-up doors. The owner John Guttridge said that the integration of the steel garage door roll-up headers on the top of each bay will match the steel work all the way down, so the retail facade will essentially look like one integrated steel face. See the project page for previous renders.

Press_Bay_Alley_1012

Press_Bay_Alley_1014

Seneca Way Eastern & Southern Facade Progress

September 26, 2013 // by Jason Henderson

EIFS base coat and finish coat texture applications are following-up right on the heels of the insulation material installation on the southern side of the Seneca Way facade. Southern side looks about half-way through, and the eastern side is nearly complete.

Seneca_Way_9231

Seneca_Way_9232

Argos Inn Open: Interior Photos on the Web

September 26, 2013 // by Jason Henderson

Right next door to the Seneca Way Project, the Argos Inn (the former McCormick Cowdry House built in 1831) has opened-up for business (bar coming soon), and they’ve posted some interior shots on their Facebook Page: Opening Week Photos

I haven’t had a chance to peek inside yet, but the exterior is absolutely great- I particularly like the application of floor to header glass along the column-lined porches on both floors. Looks like a great repurpose and restoration project for a historic building.

Argos_Inn_2013-11

Planned Parenthood Steel Structure Assembly

September 25, 2013 // by Jason Henderson

The Planned Parenthood site is showing great progress: the concrete forms have been removed on both the stair and elevator towers, and we’ve got two stories of structural steel beam assemblies, anchored on the concrete foundation sections and footer blocks. As you can see from the rendered plans below, the stair tower will be going up another story for roof access, and the steel beam section with the angled tops will be supporting the hipped-roof western portion of the building. The structure will be extending further north from what we see now to fill-out the rest of the hipped roof section and flat roof section, which will be developed just past the stair tower.

Planned_Parenthood_9231

Planned_Parenthood_9233

Planned_Parenthood_9234

Planned-Parenthood-Orthos

Collegetown Terrace Building 5 Progress & Building 6 Structure Underway

September 24, 2013 // by Jason Henderson

Well, well, I must’ve missed this one for at least a few weeks: Building 6 (see sitemap here for reference) has clearly been underway for a little while now, as the structure is up to two stories now, along with the full four stories of the block stair tower, and the retaining wall on the northern side has been wrapped. The third story floor deck is still being assembled at the far end, probably in prep for a final pour of the floor deck, but it looks as if most of the structural elements of two stories are all there, with the exception of the western end of the building, which may be framed in a different way. Building 5 shows some further progress since last week. The fourth-story framing is continuing to fill-in and the second story floor deck in the middle section (between the sheathed portions) has been poured.

The scale of this project is becoming more apparent as Building 5 has made its way around in front of the massive facade of Building 3.4. The views from the top floor of 3.4 must be quite good.

Collegetown_Terrace_9233

Collegetown_Terrace_9235

Collegetown_Terrace_9237

Collegetown_Terrace_9238

Collegetown_Terrace_9236

Collegetown_Terrace_9234

Collegetown Terrace Building 5 Framing & Scaffolding Updated Photos

September 21, 2013 // by Jason Henderson

An extra level of exterior sheathing is up on the fourth level of this section of Building 5 as framing the third level walls and fourth level deck has progressed. There’s also some more new heavy steel beam framing along the southern end of the eastern section where scaffolding has been assembled and the northern framing-out has been completed for quite a while. The insulation and waterproofing layers look just about complete on the huge northern concrete retaining wall, so it will probably be backfilled soon.

Collegetown_Terrace_91802

Collegetown_Terrace_91806

Collegetown_Terrace_91809

Klarman Hall Site Prep-Work Updated Photos

September 19, 2013 // by Jason Henderson

The future Klarman Hall’s eastern side along East Ave. has some preliminary excavation work with a small excavator and a dump truck. We’ll probably see a relatively level surface work its way down as the excavator chips away at this steep grade so that it can stay stable. Lots of soil to move though- all the more reason a concrete retaining wall will be going in this February.

Klarman_Hall_9183

Seneca Way Facade EIFS Progress

September 19, 2013 // by Jason Henderson

Seneca Way’s EIFS (Exterior insulation finishing system) facade is going up quickly, as you can see the eastern side is nearly complete, and the southern side is progressing nicely. With some more fine weather on tap for next week, I doubt this part of the project will take longer than expected. The posts with flags on the roof makes me think there’s material going up there as well, I’d bet a membrane EPDM (ethylene propylene diene monomer, lots of four-letter acronyms here). If you haven’t seen it yet, check out the website for Seneca Way, which contains full information on the amenities and floor plans.

Seneca_Way_9181

Seneca_Way_9185

Breckenridge Place Updated Photos

September 19, 2013 // by Jason Henderson

I don’t see much change on the building from the outside, so I imagine the interior is seeing most of the action this past week, however, the curbing and a few feet of road asphalt on both the Cayuga Street and Seneca Street sides has been demolished and dug-out, probably in preparation for the new sidewalks, curbs, storm drains, and landscaping.

Breckenridge_Place_9172
Breckenridge_Place_9173