Cornell Gannett Health Center Expansion

July 8, 2014 // by Jason Henderson

GoogleEarth_Image

Cornell’s Gannett Health Center will be undergoing a $55 million expansion project that will increase the total gross square footage from 35,000 to approximately 96,000 GSF by 2017. The expansion will be done in three phases for a 4-story curved wing from south to north-west along Campus Road, with an interior centered around three equally-sized Integrated Care Modules, vertically stacked on each floor (ICMs combine both primary/medical and mental health services). Cornell University Health Services sees around 90,000 annual clinical visits with a total staff around 200. The design team includes Chiang | O’Brien Architects, TG Miller P.C.Engineers and Surveyors, and Ryan Briggs Structural Engineers.

 
Gannett Health Services Building - SPR Application - Drawings - A200-C202 - 06-04-14-2

Construction Phasing:

Gannett-Const-phasing
Gannett-Const-phasing-2

The new 55,000 GSF UHSF Building (north-west corner) will be constructed in the three phases over the course of 2.5 years, and once constructed, the Gannett Center will move-in, then 22,400 GSF of the existing 35,000 GSF building will be completely renovated. In that same Phase Two, the new 18,600 GSF building at the south-east corner will be constructed. Phase Three will be a re-construction of the entrance along Ho Plaza.

Here are some shots from the submitted plans:

New-health-services-center-optimized_Page_3

New-health-services-center-optimized_Page_4

New-health-services-center-optimized_Page_1

New-health-services-center-optimized_Page_7

Gannett Health Services Building - SPR Application - Drawings - A200-C202 - 06-04-14

Here are the floor layouts for the Phase One portion of the project:

Pages from Gannett Health Services Building - SPR Application - Drawings - Phase 1 - 06-04-14_Page_1

Pages from Gannett Health Services Building - SPR Application - Drawings - Phase 1 - 06-04-14_Page_2

Pages from Gannett Health Services Building - SPR Application - Drawings - Phase 1 - 06-04-14_Page_3

Pages from Gannett Health Services Building - SPR Application - Drawings - Phase 1 - 06-04-14_Page_4

Site Plan Review Part 1
Site Plan Review Part 2
Site Plan Review Part 3
Site Plan Review Part 4

Planned Parenthood Project Photo Update

April 14, 2014 // by Jason Henderson

Photos of this Planned Parenthood of the Southern Finger Lakes project taken last week, but exterior siding and fiber-cement facade panel installation look complete, as well as recently-placed granite curbing along the drive entry and Seneca Street. It’s hard to tell from the outside, but it looks as if the walls are all framed, and electric, plumbing, and mechanicals are roughed-in, but finish-work like drop ceiling grids and drywall are continuing. Once the remaining windows, shades, signage, doors, lighting fixtures, and roofing fascia boards are installed, the building itself should look relatively complete on the outside.

This project is being constructed by LeChase Construction, and is designed by Chiang O’Brien Architects.