The metal shoring beams along East Ave appear to have been completed since early April, and the slate and metal re-roofing of Goldwin Smith Hall has progressed to the far southern edge. Foundation underpinnings for Goldwin Smith Hall will continue for the rest of this month, then further excavation of the hillside will take place along East Ave to prepare for structural foundation work for the future Klarman Hall.
Klarman Hall, Goldwin Smith Hall Photo Update
May 4, 2014 // by Jason Henderson