Rabco’s Thurston Avenue Apartments project is showing more foundation work since last time I swung around in late December. Concrete has been poured and covered for the foundation footers, and vertical rebar is in place for concrete block reinforcement. There are pallets of foam board insulation around the site to be used for foundation wall insulation once the block walls are assembled. The trenches for the foundation usually aren’t backfilled with soil until the modular pieces are secured on top of the foundations.
I’ve just learned that in fact, this project is not going to be modular, much to my amazement. An August deadline is going to be quite a difficult task for stick-built, but I suppose where there’s a will, there’s a way.

Thurston_Ave_Apartments_01271411

Thurston_Ave_Apartments_01271409

Here’s a double three bedroom unit floor plate from the site plan review documents:

Three-Bedroom-Thurston-Ave