The Purity Ice Cream project is reaching drywall-finish stage as demolition finished-up back in February, then the bathrooms, former entry, new entryway, seating, and serving areas were re-framed by Strawbridge and Jahn Builders and outfitted with mechanicals. A new trench was dug and filled across the parking lot for an improved underground power service, while all the electric was re-wired by Richardson Brothers Electric. New lighting fixtures, an entirely new HVAC system, and plumbing have been roughed-in. Drywall and cement boards have been hung, taped, mudded, and the seams were being sanded down this past week.
Stop by Purity this weekend to take a look, they’re serving 12-6
Architecture & Design by John Snyder Architects
Important Tip for this Spring: no longer a door here; new entrance will be to the right