Various shots from the Commons here over the past few days. Mostly more lateral water connection work as planned, and Bank Alley’s telecom lines were freed up from concrete to prepare for the water main and sanitary sewer work on this end. The work is starting on the south side where the metal shield is situated deep in the ground, and will progress along the trench that has been dug out. There’s already a new sanitary access manhole form in place, which was put in a few weeks ago.

Commons_Rebuild_1091

Commons_Rebuild_1092

Commons_Rebuild_1093