Building 6’s ground and second level floor decks are in the process of being poured, and the stair and elevator tower is going up on the east end. Building 5’s ground-level parking section in the east looks just about ready for the second level floor assembly, as the majority of the ground floor has been poured with concrete, and most bearing columns are up. There’s just the start of facade installation on Building 5 towards the north-western face, but the rest is either bare and wrapped sheathing, or exposed framing- the middle section looks structurally framed-out now, and exterior wall studs and plates are being installed on the northern face.
Collegetown Terrace Updated Project Photos
October 5, 2013 // by Jason Henderson