Ithaca Builds

Mapping, photos and information for Ithaca construction and development projects

Klarman Hall Structural Steel Complete

April 7, 2015 // by Jason Henderson

Hats off to Welliver and the crew from Raulli & Sons Ironworks sticking it out through the winter to get the structural steel done. Steel crane is now off site, and as the project rolls on, the new folding jib telescopic tower crane is up-and-running for the remainder of the work, especially the Josef Gartner glass installers that will be working on the glazed ceiling and wall systems that compose the atrium structure.

Throughout the structural phase, many of the exterior wall frames have now been assembled and sheathed with glass-mat sheathing in preparation for sandstone panels and various cladding types, and trades for electrical, plumbing, sprinkler systems, etc. have been busy. Interior framing started on the North side in March, and drywall and paint will be taking up much of May and June.

Photos from April 6th:
Klarman-Hall-Cornell-040615 - 3

Klarman-Hall-Cornell-040615 - 2 (1)

Klarman-Hall-Cornell-040615 - 1

Photos from March 10th:

Klarman_Hall-Cornell_Ithaca_031015 - 2

Klarman_Hall-Cornell_Ithaca_031015 - 3

klarman-atrium

Cornell_Klarman_Hall_Render

Cornell’s Klarman Hall Project Finishing Structural Steel

March 1, 2015 // by Jason Henderson

Welliver has been working away on Cornell’s 33,250 square-foot Klarman Hall Project throughout this winter, and in the next week or so, should be complete with all structural steel components. The construction has been split between the south and north sections in each phase since starting the enabling work in September 2013 and pursuant foundation excavation and foundation footings in July 2014. The two sections contain classrooms, offices, and the north section a 350-seat auditorium, and are joined by a large interior atrium, utilizing the rotunda of Goldwin-Smith Hall for seating, food/cafe counter service, and ingress/egress. Klarman and Goldwin-Smith will be combined through several connecting hallways and common areas as well, as shown in the plans below.

Since October, the structural steel contractor Raulli & Sons Ironworkers out of Syracuse have been delivering, craning, bolting, and welding the steel columns and beams into place, along with the massive atrium trusses that stretch the two main structural sections. As steel finished-up on the south section late November, crews moved-in to deck the floors with corrugated sheet metal and applied steel mesh to reinforce the concrete floor pours. Once the concrete dried in January, framers came in to frame the walls with steel studs and sheetrock the walls. According to the schedule (end of post), Josef Gartner comes on-site to mobilize this march to install the glass atrium. Once the large hoist crane for the steel is off-site, and the lane is cleared of equipment, East Ave will be opened-up to two-way traffic again by April 20th.

Speciality trades, framing, and drywall will take-up much activity on both the South and North Sections until June/July, and by the Fall, painting, building systems, and finish-work will be left to tackle. The project is slated for a December 2015 delivery.

 
Photos taken February 27th:

Klarman-Hall-Cornell-Welliver-02271504

Klarman-Hall-Cornell-Welliver-02271507

Klarman-Hall-Cornell-Welliver-02271520

Floor Plans:
klarman-hall-floor-plans-1

klarman-hall-floor-plans-2

klarman-atrium

 
Photos taken January 4th:
Klarman-Hall-Cornell-0104152

Klarman-Hall-Cornell-0104153

 
Photos taken December 14th:

Klarman-Hall-Cornell-1214146

Klarman-Hall-Cornell-1214145

Klarman-Hall-Cornell-1214141

 
Photos taken November 24th:

Klarman-Hall-Cornell-11241413

Klarman-Hall-Cornell-11241408

Klarman-Hall-Cornell-11241401

 
Photos taken November 3rd:

Klarman-Hall-Ithaca-11031405

 
Photos taken October 14th:
Klarman-Hall-Cornell-1014142

Klarman-Hall-Cornell-1014147
Klarman-Hall-Cornell-1014146

Cornell_Klarman_Hall_Render

2015-Klarman-Hall-Construction-Schedule-2

Statler Hall Entry Renovation Project Complete

October 26, 2014 // by Jason Henderson

The Statler Hall Entry Renovation has been opened-up since late August, but the interior work and all exterior finishes are now complete. Here are some final photos for the project, which began in early summer, and took out the western-facing 1987 arched limestone entryway to replace with a new limestone and glass-wrapped 450 square foot vestibule and expanded space on the second floor above. Photos throughout construction may be seen on the project category page.

General contracting services by Northland Associates out of Syracuse, NY, and design by KSS Architects out of Princeton, NJ, and M/E Engineering out of Syracuse, NY.

Photos from September 21st:
Statler-Hall-Cornell-0921147

Statler-Hall-Cornell-0921141

Photos from October 15th:
Statler-Hall-Entry-Cornell-1014141
Statler-Hall-Entry-Cornell-1014143

Photos from October 24th:
Statler-Entry-Cornell-1024141
Statler-Entry-Cornell-1024146
Statler-Entry-Cornell-1024145

Before:
Statler_Hall_Entry_1225133

Design Render:
Statler-Hall-Entry-Renovation-Render

Steel Erectors at Work on Klarman Hall

October 8, 2014 // by Jason Henderson

Cornell’s future 33,250 square foot Klarman Hall project being built by Welliver has finished-up the north and south foundations, and steel erectors are on site craning and bolting steel columns and beams in place on the south end. The columns are anchored to each foundation footing cap or pier, then the beams between each column are bolted and welded to the proper connection. The north end’s steel work should be completed by early November, and we’ll see the atrium steel assembly commence and complete throughout November.

Photos from September 29th:
Klarman-Hall-Cornell-9291408

Klarman-Hall-Cornell-9291404

Photos from October 5th:
Klarman-Hall-Cornell-1005146

Klarman-Hall-Cornell-1005143

Klarman-Hall-Cornell-1005147

Klarman-Hall---Presentation---04-24-13

Klarman Hall September Construction Update

September 24, 2014 // by Jason Henderson

The future 33,250 square foot Klarman Hall project being constructed between the wings of Goldwin Smith Hall by Welliver has completed the north and south foundation walls, and in addition to progress on the retaining foundation wall along East Ave, the southern concrete wall has been formed and poured. Because of the steep grade and excavation, concrete trucks park on East Ave and unload concrete into crane buckets that hoist the pours over to each form.

The structure represents Cornell’s first Humanities Building in over 100 years (Goldwin Smith was built in 1892). The design was done by Koetter | Kim & Associates.

Photos from September 7th:
Klarman-Hall-Cornell-0907142

Klarman-Hall-Cornell-0907145

Photos from September 16th:
Klarman-Hall-Cornell-Ithaca-09161413

Klarman-Hall-Cornell-Ithaca-09161407
Klarman-Hall-Cornell-Ithaca-09161405

Photos from September 21st:
Klarman-Hall-Cornell-0921146

Klarman-Hall-Cornell-0921141

Klarman-Hall---Presentation---04-24-13

Statler Hall Entry Renovation Nearing Completion

September 16, 2014 // by Jason Henderson

Cornell’s $2.4 million Statler Hall Entry Renovation project seems to be nearing completion: the exterior limestone veneer facade sections are installed, and the second floor interior ductwork and mechanicals have been wrapped in insulation. Next up are final touches to the exterior- aluminum trim work between the glass curtain wall, roof fascia, stone base sill, bike racks, and the remainder of the interior finishes.

The design is by KSS Architects and M/E Engineering, and the project has been managed in-house by Cornell Facilities Services.
The renovation is intended to match the additions that have been completed on the eastern and southern sides: the Beck Center along the eastern side (Phase One Expansion), and the renovated auditorium tower on the southern side (Phase Two expansion). KSS Architects designed both the Beck Center and the Tower Renovation

Photos from September 1st:
Statler-Hall-Entry-Cornell_0901148
Statler-Hall-Entry-Cornell_0901147

Photos from September 7th:
Statler-Hall-Entry-0907145

Photos from September 15th:
Statler-Entry-Cornell-Ithaca-0916146
Statler-Entry-Cornell-Ithaca-0916143
Statler-Entry-Cornell-Ithaca-0916142

Before Photo:
Statler_Hall_Entry_1225133

Klarman Hall August End Photo Update

September 3, 2014 // by Jason Henderson

Cornell’s future 33,250 square foot Klarman Hall Project being constructed by Welliver has continued progress on the concrete wall along East Avenue and the south foundation walls. The shoring wall along East Ave (driven into place over the summer) holds the soil back as rebar is assembled, then large steel forms are craned in place and secured, and concrete is poured section-by-section going south to north. It’s hard to make out the status of the north foundation walls, but looking at the schedule, we should see rebar assembly there shortly. The south foundation walls have been completed, and steel erection above these walls should begin soon. Photos from August 20th and September 1st below:

Photos taken August 20th:

Klarman-Hall-Cornell-0821141
Const-Schedule-thru-Sept-2014
Klarman-Hall-Cornell_08201403

Klarman-Hall-Cornell_08201404

Photos taken September 1st:

Klarman-Hall-Cornell_0901147

Klarman-Hall-Cornell_0901144

Klarman-Hall-Cornell_0901142

Klarman-Hall---Presentation---04-24-13

Design by Koetter | Kim & Associates

Statler Hall Entry Nearing Completion

August 22, 2014 // by Jason Henderson

Cornell’s $2.4 million Statler Hall Entry Renovation is wrapping-up, as work crews finished hanging glass on the curtain wall, all exterior framing, graded and poured cement walkway, stone walls, stone base facade, and metal facade panels this past week. The new entry houses an expanded ground floor entry vestibule, additional second floor space, and significant mechanical and HVAC upgrades. The design was done by KSS Architects, whom completed the designs for the previous Beck Center and Statler Auditorium and Tower Renovations. The original limestone-clad building was completed in 1949.

Photos from August 14th:
Statler-Hall-Cornell-Ithaca-0814146

Photos from August 20th:

Statler-Hall-Cornell-2_0820142

Statler-Hall-Cornell-2_0820144

Statler-Hall-Cornell-2_0820145

Statler-Hall-Cornell_0820142

Statler-Hall-Entry-Renovation-Render

Klarman Hall Mid-August Photo Update

August 16, 2014 // by Jason Henderson

Here’s a photo update (July 29th to August 14th) for Cornell’s 33,250 square-foot Klarman Hall project, a new Humanities building to be situated between the wings of Goldwin Smith Hall along East Avenue. Over the past few weeks, rebar and concrete forms for the south end and north end footings have been assembled and the south end footings and western foundation walls look partially completed. The shoring wall along East Ave is being prepped for pouring concrete as well, as large steel concrete forms are craned into position to sandwich the rebar assemblies between the form and shoring wall. Steel erection over top of the south end’s foundation walls begins later this month, and by mid-September, the north end foundation walls will be completed and ready for structure assembly.

The building is designed by Koetter | Kim & Associates, with construction by Welliver.

July 29th:

Klarman_Hall_Cornell_07031401

August 3rd:

Klarman_Hall_Cornell_07031403

August 6th:

Klarman-Hall-Cornell-Ithaca-0806146

Klarman-Hall-Cornell-Ithaca-0806144

August 14th:

Klarman-Goldwin-Hall-Cornell-Ithaca-08141401

Klarman-Goldwin-Hall-Cornell-Ithaca-08141403

Klarman-sidewalk

Klarman-Hall---Presentation---04-24-13

Klarman-schedule

Statler Hall Entry Renovation Early August

August 11, 2014 // by Jason Henderson

Updated photos here from August 3rd and August 6th for Cornell’s Statler Hall Entry Renovation project that has been going on this summer (infill project for a new 450 square foot vestibule and also second floor space above). At this pace, I’m sure a lot more has been done since the time this is posted: the exterior wall framing looks to have been completed by the end of July, along with fiberglass sheathing around the support wall and side wall. The interior shows rapid HVAC and electric installation, and the glass curtain wall has been assembled well beyond halfway in the span of about four days. Design by KSS Architects, and project being managed in-house by Cornell Facilities Services.

August 3rd:

Statler_Hall_Entry_Reno_Cornell_0703142

August 6th:

Statler-Hall-Cornell-Ithaca-0806146

Statler-Hall-Cornell-Ithaca-0806143

Statler-Hall-Cornell-Ithaca-0806141

Statler-Hall-Entry-Renovation-Render