Ithaca Builds

Mapping, photos and information for Ithaca construction and development projects

Gates Hall

The Gates Hall Facade

October 15, 2014 // by Jason Henderson

Quite possibly the most unique-looking building in Ithaca, the recently dedicated Gates Hall wears a facade mainly composed of glass curtain wall with an assortment of flat and angled metal shading panels produced by a company out of Kansas City, Missouri: Zahner. The group just released a nice web page detailing the design and installation process with the Architecture Team from Morphosis, the General Contractor Welliver, Structural Engineering firm Thornton Tomasetti, and glass installer W&W Glass.

As facade systems have become more complex, the process has evolved to work-out as many pre-fabrication steps before arrival on-site, then as panels are installed, photos from the site are compared with the full 3D model for verification. The same technique was actually employed for the new Barclays Center in Brooklyn, designed by SHoP Construction. In addition to the aesthetic purpose, the panels actually block a precisely calculated portion of sunlight to limit solar gain (too much extra heat from the sun, driving up cooling needs).

Gates-Hall-Cornell-1014141

Gates-Hall-Cornell-1014144

Cornell Gates Hall Interior Photos

May 1, 2014 // by Jason Henderson

Got a chance to swing into Gates Hall and take some more interior photos since last time, so here are some shots from the hallways, common areas, and a few rooms. Not sure when the steps out front will be completed, but the interior has some nice eye-candy, and a great view of Hoy Field.

Ithacating has a great shot of this project from back in late 2012 when it was still being framed; here’s a shot from April of last year, and here are some photos from July. Definitely an interesting place to walk through:

 

Gates-Hall-Cornell-Ithaca-05011424

Trippy Hallways:
Gates-Hall-Cornell-Ithaca-05011412

Open cell ceiling panels, handy for maintenance:

Gates-Hall-Cornell-Ithaca-05011408

Common Areas:
Gates-Hall-Cornell-Ithaca-05011417

I was hoping this would be translucent, but it’s too opaque to see through. This is the glass floor of the cantilever section:

Gates-Hall-Cornell-Ithaca-05011416

Gates-Hall-Cornell-Ithaca-05011423

Gates-Hall-Cornell-Ithaca-05011415

Work Rooms and Labs:
Gates-Hall-Cornell-Ithaca-05011405

Gates-Hall-Cornell-Ithaca-05011402

Gates Hall Move-ins Begun & Lobby Photos

February 12, 2014 // by Jason Henderson

Cornell’s Gates Hall is just about complete, and move-ins for the Information Science Department have begun for faculty, staff, and a few classrooms/workspaces are set up. It’s pretty wild on the inside, and the entryway cantilever provides an interesting preview of that (plus, when the weather is nicer, I think it would provide a nice assembly space). The lobby features semi-transparent glass, through which you can see the stairs up to each level, and clear glass panels for glimpses of each floor.

Many of the rooms are still being put together, but much of the common area furniture is already setup for use. Besides the concrete features on the outside, I didn’t see any finishes on the inside that aren’t completed, although I bet there’s much work to be done moving everything over, hooking up computers and networks, etc. Moving an entire department must be challenging. Floors are concrete, much like Milstein Hall, and there’s a bold amount of glass and steel everywhere. I’ll surely be coming back soon to explore much more- especially to walk around on the transparent floor at the end of the cantilever- vertigo anyone?

Gates_Hall_Cornell_Ithaca_02091420

Gates_Hall_Cornell_Ithaca_02091401

Gates_Hall_Cornell_Ithaca_02091409

Gates_Hall_Cornell_Ithaca_02091413

Gates_Hall_Cornell_Ithaca_02091406

Gates_Hall_Cornell_Ithaca_02091407

Gates Hall Photo Update

December 30, 2013 // by Jason Henderson

Cornell’s future home for the CIS program, Gates Hall has made some exterior progress since late November, however, I’ve noticed that the facilities page now indicates (on the right-hand side) that early 2014 is the scheduled opening, rather than December 2013 as previously announced. The angular south-west entry way retaining walls have been poured, the stair structure and rebar is in place, and a couple more pre-fab concrete “feet” have been assembled on the western entryway. I imagine that the interior has been the major focus for finishing-up to get the school moved-in; Spring instruction starts January 22nd, although, judging by peaks from the outside, the goal may be during semester.

Gates_Hall_12251308

Gates_Hall_12251303

Gates_Hall_12251310

Gates Hall Continues Looking Cool

November 28, 2013 // by Jason Henderson

The entry structure is really coming together now, and with the fencing down, the view from the street is fantastic. There’s a bit of framing to form concrete for the stepped entry along the southeastern end where the sign for the building will be attached. The entryway on that side will match the shape of the cantilever above to create an interesting perspective.

Gates_Hall_112405

Gates_Hall_112403

Gates_Hall_112410

Gates_Hall_Render

Gates Hall at Night

November 7, 2013 // by Jason Henderson

These came out quite grainy, but hopefully they give a sense of what this building looks like at night. With all the glass, it’s lit-up like a Christmas tree on every floor, and I imagine the new entryway will have a bunch of floods illuminating the cantilever ceiling, as well as plenty of spots lighting the entryway. Speaking of the entry, the feet-structures are still coming along, and there’s a new concrete wall along the corner of Hoy and Campus Roads, where the level entry will be (the opposing side will have stairs from the sidewalk, shown below).

Gates_Hall_Night_11072

Gates_Hall_Night_11073

Gates_Hall_Render

Gates_Hall_Night_11076

Gates Hall Construction Fence is Down, Nice Views

October 15, 2013 // by Jason Henderson

The construction fence outside Gates Hall has been taken down and now you can get a really good perspective of what this building looks like. The entryway has been ongoing since around July, and there was a contractor working on the ceiling panels of the cantilever when I stopped by; there will be a section of what looks like a steel-reinforced glass floor (see render below) for those that like to tempt feelings of vertigo. There’s a bunch of rebar and rebar sheets stacked on the site, so I think part of the fence being taken down is to make room for trucks to compact the soil and start hardscaping for the rest of the entry. There’s also new curbing all the way around the site edges, and new asphalt.
Got a chance to see the infamous Thomas Mayne/Morphosis Cooper Union 41 Cooper Square project this weekend in NY- it’s wild in person, especially at night, as I imagine Gates Hall will be (Morphosis designed Gates Hall, as well as an impressive slew of other high-profile insitutional/corporate projects- see the Giant Interactive Campus in Shanghai; they’re also designing Cornell’s NYC Tech Campus)

Gates_Hall_101504

 

Gates_Hall_Render

 

Gates_Hall_101506

 

Gates_Hall_Render_2

 

Gates_Hall_101510

Gates Hall Updated Entry Photos

October 6, 2013 // by Jason Henderson

More entry assembly work here, and the swooped ceiling panels look completed, providing a nice contrast to the exterior facade. The construction should be finishing up in December so that SCI can move-in January to be ready for the Spring 2014 semester.

Just learned some new info here: the metal shading structures on the exterior facade are done by the A. Zahner Company, a firm out of Kansas City, MO that fabricates custom metalwork for projects all over the world.

Gates_Hall_1022

Gates_Hall_1024

Gates Hall Updated Photos

September 16, 2013 // by Jason Henderson

Just some updated photos of Gates Hall from last week- entryway “feet” are growing. Wonder how heavy those concrete blocks are..

Gates_Hall_9102

Gates Hall Entry Work

September 6, 2013 // by Jason Henderson

Not much to see here on the outside, but the entryway work has a couple more feet-like steel structures in place, and you can see a nice-looking woodgrain ceiling application underneath the cantilever. Excited to see the final product; without a doubt, it will probably be one of the coolest entries of any building in Ithaca.

Gates_Hall_9421

Gates_Hall_9425